OZ Minerals: A Year of Delivery
Carrapateena airstrip. All images: OZ Minerals BY JESSICA CUMMINS ON the back of a productive year, OZ Minerals remains focussed on developing one of Australia’s largest copper gold resources, Carrapateena, with first concentrate scheduled in 2019. As the Adelaide-based miner moves its Carrapateena project towards production, a number of key activities remain on the table. After injecting $85 million into the project during the September quarter, the miner saw the completion of its first ventilation raisebore and commenced development on the crusher level. OZ Minerals chief executive Andrew Cole said flights to the site had begun and construction of all 556 rooms at the Tjungu accommodation village were also completed. “The mineral processing plant and non-processing infrastructure construction is continuing as per schedule,…