Underground Mining Recommences At Red 5’s KOTH Project
Red 5 Limited (ASX: RED) remains on track for first gold production in the current quarter at its 100%-owned 2.4Moz, 16-year life-of-mine King of the Hills (KOTH) Gold Project, after achieving further key construction and operational readiness milestones during March 2022. Construction and Commissioning Key construction progress for March included: Commissioning of the crushing circuit has been completed; Commissioning of the gas pipeline has been completed; Commissioning of the power station has been completed to the stage where it is ready to power the process plant; Installation of the solar panels has been completed and wiring is being finalised; and Commissioning of the SAG mill has commenced, with the current critical path to first gold being the commissioning of the…