Mount Gibson Iron: Starting Fresh
By October 2018, the water level at the main pit was down about 20m from where it was when Mt Gibson began dewatering. Image: Mount Gibson Iron. THE rebuild at Koolan Island is now 90 per cent complete and on track for completion in March next year, less than five years after Mount Gibson Iron was forced to close it following extensive flooding. Amy Blom spoke with incoming Mount Gibson Iron chief executive Peter Kerr about the rebuild and what else lies on the horizon for the miner. Q. Koolan Island closed in 2014 following extensive flooding. What led to the decision to rebuild the seawall? Mount Gibson approved the rebuild of the seawall in April 2017 after two years…